PENERAPAN ANALISA MANAJEMEN WAKTU DENGAN METODE CPM DAN PERT PADA PROYEK PEMBANGUNAN PUSKESMAS LOA PARI DI KECAMATAN TENGGARONG

ZAKY FACHRIDHIA JASMAN

Abstract


Project activities Loa Pari subdistrict health center construction Tenggarong Seberang, Tenggarong Regency, East Kalimantan includes preparatory work, excavation and foundation work, structural work, floor and ceramic works, wall and plaster work, roof and ceiling work, frame work, hanger and lock work, painting work, sanitary work, mechanical work. and electrical, garden work, miscellaneous work. To adjust the project duration required project control. Project control is a way of controlling all activities using specific techniques and methods in an effective manner. So that it can be seen how long it will take a project to be completed and look for the possibility of accelerating the project implementation time with the Network Planning method. Network Planning is one of the models used in. The goal of PERT is the achievement of a certain level where time is an important basis for PERT in the completion of activities for a project. In the method PERT and CPM major problem which is a technique for determining the fee schedule of activities along with your budget with the intention of jobs that have been scheduled that can be completed in a timely manner as well as the exact cost. calculation results obtained ΣV (te) = 5.278, S = 2.639, T (d) = 110 days, Z = -3. For the results of the estimated time of completion of the project from the CPM analysis results obtained 117 days, the results of the PERT analysis were obtained 118 days, the results of calculations using the MS Project obtained 117 days.

Keywords


Method CPM, PERT, MS Project, ∑▒〖V (te)〗, S, T(d), Z

Full Text:

pdf

References


Anggara, H. 2005. Perencanaan dan Pengendalian

Proyek dengan Metode PERt-CPM: Studi

Kasus Fly Over Ahmad Yani, Karawang.

Journal the Winners, Vol. 6, No. 2: 155-174.

Dannyanti, E. 2010. Optimalisasi Pelaksanaan

Proyek dengan Metode Pert dan CPM (Studi

Kasus Twin Tower Building Pascasarjana

Undip). Skripsi, FT Undip. Semarang.

Muhamad, Amiruddin HI. 2013. Optimalisasi

Pelaksanaan Proyek dengan Metode PERT

dan CPM (Studi Kasus di Gedung SMA

Negeri 1 Tidore Kepulauan, Provinsi Maluku

Utara). Skripsi. Fakultas Teknik, UMY.

Yogyakarta.

Ridho, M. Rizki & Syahrizal. 2014. Evaluasi

Penjadwalan Waktu dan Biaya Proyek dengan

Metode PERT dan CPM (Studi Kasus: Proyek

Pembangunan Gedung Kantor Badan Pusat

Statistik Kota Medan di Jl. Gaperta Medan,

Sumatera Utara). Jurnal Teknik Sipil USU,

Vol. 3, No. 1.

Sahid, Dadang S.S. 2012. Implementasi Critical

Path Method dan PERT Analysis pada Proyek

Global Technology for Local Community.

Jurnal Teknologi Informasi dan Telematika,

Vol. 5: 14-22.

Schwalbe, Kathy. 2004. Information Technology

Project Management. Edisi Ke-4. Course

Technology, Inc. Boston.

Soeharto, I. 1999. Manajemen Konstruksi dari

Konseptual Hingga Operasional. Erlangga.

Jakarta.

Subagya. 2000. Analisis Manajemen Proyek. Graha

Pena. Bekasi.

Susilo, Yayuk Sundari. 2012. Analisis Pelaksanaan

Proyek dengan Metode CPM dan PERT (Studi

Kasus pada Proyek Pelaksanaan Main Stadium

University of Riau). Jurnal Fakultas Teknik

Sipil Universitas Riau: 1-16.

Tampubolon. 2004. Pedoman Manajemen Proyek.

Jilid 1. Afj Mobicons. Malang.

Taurusyanti, D. & Lesmana, M.F. 2015.

Optimalisasi Penjadwalan Proyek Jembatan

Girder Guna Mencapai Efektifitas

Penyelesaian dengan Metode PERT dan CPM

pada PT Buana Masa Metalindo. Jurnal Ilmiah

Manajemen Fakultas Ekonomi, Vol. 1, No. 1

Tahun 2015: 32-36


Refbacks

  • There are currently no refbacks.


VOL 1. NOMOR 1. AGUSTUS 2012